Progress report - October 28 |
|
|
|
|
Written by Ron B
|
|
Saturday, 28 October 2006 |
 Twin guest rooms |  Staff room and car parking |
Willem has senet this set of photos as a progress report. For the first time we see the additonal buildings. On the left are the twin guestrooms, and on the right is the staff room and car space.
 Main house with filling |  Main house looking north east |
Here we see the stone foundations up to floor level (75 cm) are complete and the earth fill has been added to bring it up to the floor level.  Main house looking north west |  Pool |
The left photo is another view of the main house looking north-west, and on the right is a view of the pool near to the front fence.
mosimage}
|  Pool and punp room
|
On the left we are looking sideways (east) across the pool and the higher wall is that of the pump room beneath the bengong. On the rigth we are looking from teh main house back (south) to the twin guest rooms.  Pool again |  Looking from main house back too guiest rooms |
Her are two shots from the guest rooms - the left one is looking straight to the bach (north) while the right one is looking north west.
|
|